Hey folks, let’s get to it!

The Bits

Completed ToDo List Items:

  • Serial connection monitor+restart

  • Convert cone movement steps into the command syntax that the Arduino runtime expects

  • Interface: Complete a unified menu system so any function can be accessed from any view.

Follow along with the the todo list on the project board @ https://github.com/margyle/MugsyDev/projects/2

Next Steps:

  • I’ll be going into more detail on the above completed items and how they work in an upcoming update.

  • The bulk of this upcoming week will be focusing on code clean up. I’ve been digging though this while working on todo list items so I have a much better idea of what’s required to get everything ready for GitHub. There is a lot of organizational work that needs to be done here. I’m pushing to have this completed by Thursday.

  • No updates on PCBs just yet.

Shipping Outlook:

  • I think it is very likely that we will have 5-10 units out before the end of this month.

  • I do not yet feel comfortable making estimates beyond those 10 units but as we get through the next 2 weeks I will have more info to go on.

Updates:

  • The next update will be out on Thursday or Friday. If something important pops up before then I will send out a quickie.

  • This update will hit the KS page at some point on Monday (3/8).

Thanks!