Hey folks, hope all is well out there. Here is the updated estimated shipping timeline:

  • Target shipping date: Week of 4/21

  • 4/1-4/7:

    • PCB: Finalize layout of primary PCB and send to fab by Thursday, the 4th. All pin assignments have been finalized and I have resolved the last blocker, a discrepancy between the RJ45 jack I’ve sourced and the footprint’s anchor hole position.

    • Models: Upload remaining CAD files to the design repo.

  • 4/8-4/14:

    • 4/11: Open the Cloud Control beta test to the beta group.

    • All week: ongoing brew testing, MugsyOS organization and release prep.

  • 4/15-4/21:

    • Code release.

    • MVP assembly docs.

    • Start recording basic usage demo and walkthrough for all primary functionality.

    • Contact first batch recipients.

  • 4/21-4/28:

    • Release demo/instructional walkthrough.

    • Pack and ship first batch. Target quantities: 5 kits, 1 assembled.

  • Post shipment: Discuss next steps, shipping ramp up expectations, user feedback results.