Quickie.

Hey folks! Just a couple of things to hit tonight:

  • Software work has continued and I have completed 40-50% of the remaining items. I expect to hit 100% by the end of this upcoming weekend. Github pushes will hit this weekend as well.

  • As of today, I am still confident that we will be shipping kits with 7-10 days. As long as no blockers pop up, new ETAs will be going out this weekend.

  • I have published an update to Kickstarter that covers the important bits from the last several weeks of blog posts.

  • The last day or two I spent a few hours repairing the laser as the most recent replacement tube had a flaw and fizzled out. While I have it open, I’m updating lenses and mirrors as well as adding an ammeter. I will finish the main wiring tomorrow as I am waiting on high voltage connection kit (20,000 volts!) from Amazon. Once that’s done I’ll be back cutting panels…

Ok, that is all for now. Next update will be this weekend unless there is something significant to share. Thanks!

MComment